PPAP submission levels (1–5) & 18-element checklist
Check which of the 18 AIAG PPAP elements must be submitted to your customer (S), retained on site (R) or defined by customer-specific rules (*) for Levels 1 through 5.
Select your customer's PPAP submission level
PSW with product samples and complete supporting data. Level 3 is the default AIAG submission level unless the customer specifies otherwise.
- Submit to customer (S)
- 16 elements
- Retain on file (R)
- 2 elements
- Customer-defined (*)
- 0 elements
| # | PPAP element | Action | What inspectors check |
|---|---|---|---|
| 1 | Design Records | S · Submit to customer | Authorized drawing, CAD model or specification (plus ballooned print matching dimensional results). |
| 2 | Engineering Change Documents | S · Submit to customer | Authorized engineering change notices not yet incorporated into the design record. |
| 3 | Customer Engineering Approval | S · Submit to customer | Evidence of customer engineering approval when specified by the design record. |
| 4 | Design FMEA (DFMEA) | S · Submit to customer | Failure Mode and Effects Analysis when the organization has design responsibility. |
| 5 | Process Flow Diagrams | S · Submit to customer | Sequence of manufacturing, inspection and packaging operations from receiving to shipping. |
| 6 | Process FMEA (PFMEA) | S · Submit to customer | Process Failure Mode and Effects Analysis covering every manufacturing/inspection step. |
| 7 | Control Plan | S · Submit to customer | Written summary of process controls, inspection methods, sample sizes and reaction plans. |
| 8 | Measurement System Analysis (MSA) Studies | S · Submit to customer | Gage R&R, bias, linearity and stability studies for measurement equipment in the Control Plan. |
| 9 | Dimensional Results | S · Submit to customer | Measured values for every ballooned characteristic on the design record across required sample pieces. |
| 10 | Material / Performance Test Results | S · Submit to customer | Raw material mill certs, special process certs and functional/performance test reports. |
| 11 | Initial Process Studies | S · Submit to customer | Short-term capability studies (Cpk / Ppk) on special characteristics designated by customer or team. |
| 12 | Qualified Laboratory Documentation | S · Submit to customer | Scope and accreditation (e.g. ISO/IEC 17025) for internal or external testing laboratories used. |
| 13 | Appearance Approval Report (AAR) | S · Submit to customer | Required when the part has customer-specified color, grain, gloss or appearance criteria. |
| 14 | Sample Production Parts | S · Submit to customer | Physical sample parts taken from the significant production run. |
| 15 | Master Sample | R · Retain at manufacturing site | Signed/dated physical reference sample retained for operator comparison (when applicable). |
| 16 | Checking Aids | R · Retain at manufacturing site | Part-specific fixtures, templates, mylars or attribute gages used in production inspection. |
| 17 | Records of Compliance with Customer-Specific Requirements | S · Submit to customer | Evidence fulfilling OEM-specific quality addenda (CSR). |
| 18 | Part Submission Warrant (PSW) | S · Submit to customer | Summary sign-off form declaring part conformance, submission reason, weight and level. |
How PPAP dimensional results link to your ballooned drawing
Element 1 (Design Records) and Element 9 (Dimensional Results) require a ballooned print where every characteristic number matches the dimensional results table across all submitted sample parts. Always verify customer-specific requirements (CSRs) and any OEM-mandated warrant format before final approval.
Prepare PPAP working copies from your ballooned drawing
BalloonFAI Pro pairs your ballooned PDF and Form 3 requirements with CMM measurement import (CSV, PC-DMIS, Q-DAS, ZEISS CALYPSO) and multi-sample PPAP working copies containing a warrant draft, evidence index and sample matrix.